Prince2 Project Management Explained!

PRINCE2 project management methodology is aexisting stage plan due to slippage or other unforeseen
process-driven project management method whichcircumstances. Also covered is the way in which the
contrasts with reactive/adaptive methods developedboard can give ad hoc direction to a project and the
by Office of Government Commerce (OGC).way in which a project should be closed down.
PRINCE2 defines 45 separate sub-processes andControlling a stage (CS)
organizes these into eight processes as follows:PRINCE2 project management method suggests that
Starting up a project (SU)projects should be broken down into stages and these
In this process the project team is appointed and asub-processes dictate how each individual stage
project brief (describing what the project is going toshould be controlled. Most fundamentally this includes
achieve and the business justification for doing so) isthe way in which work packages are authorized and
prepared. In addition the overall approach to be takenreceived. It also specifies the way in which progress
is decided and the next stage of the project is planned.should be monitored and how the highlights of the
Once this work is done, the project board is asked toprogress should be reported to the project board. A
authorize the next stage, that of initiating the project.means for capturing and assessing project issues is
Planning (PL)suggested together with the way in which corrective
PRINCE2 project management method advocatesaction should be taken. It also lays down the method
product based planning which means that the first taskby which certain project issues should be escalated to
when planning is to identify and analyze products.the project board.
Once the activities required to create these productsManaging product delivery (MP)
are identified then it is possible to estimate the effortThis process consists of three sub-processes and
required for each and then schedule activities into athese cover the way in which a work package should
plan. There is always risk associated with any workbe accepted, executed and delivered.
and this must be analyzed. Finally, this processManaging stage boundaries (SB)
suggests how the format of plans can be agreed andThe Controlling a Stage process dictates what should
ensures that plans are completed to such a format.be done within a stage, Managing Stage Boundaries
Initiating a project (IP)(SB) dictates what should be done towards the end of
This process builds on the work of the Start Up (SU)a stage. Most obviously, the next stage should be
activity and the project brief is then form into aplanned and the overall project plan, risk log and
Business Case. The approach taken to ensure qualitybusiness case amended as necessary. The process
on the project is agreed together with the overallalso covers what should be done for a stage that has
approach to controlling the project itself. Project filesgone outside its tolerance levels. Finally, the process
are also created as is an overall plan for the project. Adictates how the end of the stage should be reported.
plan for the next stage of the project is also created.Closing a project (CP)
The result can be put before the project board forThis covers the things that should be done at the end
them to authorize the project itself.of a project. The project should be formally
Directing a project (DP)de-commissioned (and resources freed up for
These sub-processes dictate how the Project Boardallocation to other activities), follow on actions should
should control the overall project. As mentioned above,be identified and the project itself be formally
the project board can authorize an initiation stage andevaluated.
can also authorize a project. Directing a Project alsoFind out more about Prince 2 Project Management
dictates how the project board should authorize aTraining - Myth & Misconceptions here.
stage plan, including any stage plan that replaces an